Hi Gurus!

I am facing an issue when excute MRP for a Finished Good Make to order which has a component MTO. there is enough stock for Component, the expected is that a planned order for the component should not be raised. when MPR is executed i am getting an planned order for Finished good material which is fine but i am getting a planned order for the component too.

FG MTO :

MRP TYPE : PD
Strategy group 20 :

Componente
MRP Type : PD

any help is welcome
:S